The work to be completed this summer includes replacement of sections in red, partial replacement of yellow sections, replacement of roof and flashing on the stair towers, and repair of front siding, doors and trim.
A big THANK YOU to all who contributed to this massive undertaking!
Illustration by Preservation Timber Framing
The steeple is supported by the wooden frame installed for the duration of the repair.
Digging into the tower box left post.
What an undertaking!!
The Deterioration Exposed
Beautiful new sills!
Preparing new and old trim to be pieced back together.
New post sections
Old Post Sections
Amazing work by a Master Craftsman!
The front windows were carefully removed to make way for the temporary supports.
David uses the tractor to move the 12x12s for cutting and positioning for placement.
How did we span nearly 40 feet of 12×12 vertical post?
Two sections – one with double bladed scarf joints rotated 90 degrees for added stability.
This is the first section that was placed at the top of the left tower post between original construction and the second section, which runs down to the sill.
Amazing work by The Steeple People!
Eli cutting scarf joints for the new left 12×12 tower post.
Spirelets waiting to go back up.
Hand carved pegs
12x12s laid out ready to cut and place in the left stair tower
Staging removed, September 7, 2022